Waller Road East / 128th Street East (CRP 5633)

Waller Rd E / 128th St E Intersection Banner

What's Happening


Pierce County hosted the Pre-Construction Meeting on July 6, 2017, and anticipates issuing the Notice to Proceed in late July. When the work begins, the Contractor, Northwest Cascade, Inc., will be on-site performing the following work:
  • Installing erosion control measures
  • Clearing and grubbing
  • Beginning work in the stormwater detention pond
  • Roadway excavation
  • Storm sewer installation

About the Project


This project provides improvements to the Waller Road East / 128th Street East (CRP 5633) intersection by constructing a fully actuated traffic signal system with left turn lanes on all four legs of the intersection and paved shoulders with asphalt barrier curb. The improvements include modification to the existing Clover Creek Stormwater Detention Pond and installation of water quality treatment facilities. This work includes but is not limited to, clearing and grubbing, roadway excavation and embankment, crushed surfacing, hot mix asphalt, enclosed storm drainage conveyance system, and other work.

Project Timeline


April 28, 2017: Bid Opening date

May 09, 2017: Pierce County awarded the contract to 
Northwest Cascade, Inc.  

July 06, 2017:
 Pierce County hosted the Pre-Construction Meeting

July 2017:
 Anticipated Notice to Proceed

Fall 2017:
 Anticipated Substantial Completion

Winter 2018:
 Anticipated Physical Completion

Contact Us
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Northwest Cascade, Inc.
Contractor
Phone: (800) 444-2371
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
10412 John Bananola Way East Puyallup, WA 98374