14th Avenue NW - 24th St NW to Cushman Trail (CRP 5812)

14th Ave NW (24th St NW to Cushman Trail) Banner

What's Happening


Engineering: We're continuing preliminary design of a new sidewalk along the west side of 14th Avenue NW (CRP 5812)

About the Project


When constructed, the 0.53 miles of sidewalk will connect along 14th Avenue Northwest from 24th Street Northwest to the Cushman Trail (CRP 5812). The new sidewalk is planned to include:
  • A 6-foot wide pervious cement concrete sidewalk.
  • 2-foot wide gravel shoulders on each side of the sidewalk.
  • A 5-foot wide buffer between the edge of the sidewalk and the edge of the existing paved shoulder.

Project Timeline


July 2015 to October 2016:
Surveying, preliminary design, plans, and estimate, completed.

October 2016 to February 2017: Project on hold.

February 2017 to August 2017: Interim project options evaluated.

August 2017 and Beyond: Complete preliminary engineering, right-of-way acquisition, environmental documentation, final plans, specifications, and construction.