2016 Asphalt Overlay Program (CRP 5820)

Header image of neighboorhood street

What's Happening


Major construction is complete in all but two locations, Spanaway Loop Rd. S. and Steele St. S. (groups 1 and 5). The contractor, Puget Paving and Construction, is installing traffic markings on the roadway surface and preparing to pave Steele St. S.

About the Project


This project involves pavement resurfacing and sidewalk ramp upgrades at various locations (also called "Groups") throughout the County. In Group 6, we are using an innovative process of Crack and Seat prior to pavement resurfacing. The locations include:
Group 1:
Spanaway Loop Rd S (174th St S to Military Rd S)
Group 2:
Spanaway Loop Rd S (120th St S to 100' n/o 116th St S)
Group 3:
Portland Ave E (540' se/o 18th Ave E to 104th St E)
Group 4:
Portland Ave E (112th St E to SR-512 EB Ramp)
Group 5:
Steele St S (SR-512 WB Ramp to 102nd St S)
Group 6:
108th St S (Ainsworth Ave S to Pacific Ave S)
Group 7:
66th St W (200' w/o 53rd Ave W to Tacoma City Limits)
Group 8:
Gem Heights Dr E (Silver Creek Ave E to Meridian Ave E)
Group 9:
Pioneer Way E (Bentley Rd E to 320' nw/o 72nd St E)
Group 10:
Rhodes Lake Rd E (320' ne/o Falling Water Blvd E to 198th Ave E)
Group 11:
Waller Rd E / 104th St E (Intersection)

Project Timeline



April 22, 2016: Bid Opening

May 03, 2016: Pierce County awarded the contract to Puget Paving

June 13, 2016: Pierce County hosted the Pre-Construction Meeting

July 5, 2016: Pierce County issued the Notice To Proceed

May 2017: Anticipated Substantial Completion

June 2017: Anticipated Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Puget Paving
Contractor
Phone: (253) 474-5616

Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
10817 26th Avenue South
Lakewood, WA 98499