Project Description


Development of a warehouse/ industrial park facility on a 162 acre site located within the Employment Center Zone (EC), an allowed use consistent with the zoning classification. A Shoreline Substantial Development (SD) is required for the storm outfall and trail improvements.

Two Phased Project with a building total of 2,605,000 square feet and include associated grading, paved parking, and required infrastructure on the 7 lot short plat.
  • Phase I
    • Buildings A-E, with a cumulative square footage of 2,124,000 and associated parking
  • Phase II
    • Buildings F & G with a cumulative square footage of 437,000 square feet and associated parking

The project will be located outside of the 46.95 acres located within the 100 ­year floodplain of the Puyallup
River.

History

November 26, 2014 applications were made for a Business Park: 
  • Preliminary Short Plat (SP)
  • Planned Development District (PDD), Cancelled at Applicant's request
  • Environmental Checklist (SEPA)
  • Administrative Design Review (ADR)
  • Shoreline Substantial Development Permit (SD)

Notice of Application (NOA) was distributed to reviewers, cities, and adjacent property owners:
  • December 4, 2014
  • June 17, 2016
  • September 26, 2016

March 31, 2016 Applicant requested that the Planned Development District be canceled.

September 12, 2016  A revised submittal package was received showing to reflect requirements per the studies requested.


  

dashboard.gif


Applications

map.gif
Maps

regs.gif
Regulations
reports.gif

Reports & Studies


NEED MORE INFORMATION OR HAVE QUESTIONS?
Please contact Marcia Lucero, Project Manager, in the Current Planning Section of Planning and Land Services, at mlucero@co.pierce.wa.us or at (253) 798-2789.