About the Project
Work on this project to improve safety and operations at the T-shaped intersection, which is located west of Naches Trail Elementary School, began in August 2018.
In 2018, crews cleared portions of the project site, began widening the south side of 152nd Street East and built the stormwater detention pond. Utility companies also relocated utility lines.
Earlier in 2019, about 600 feet of 22nd Avenue East from where it intersects with 152nd Street East was rebuilt. Crews also constructed sidewalks along 22nd Avenue East and curb ramps at the intersection, installed new crosswalks, and added new street lights, curbs and gutters.
Active Construction, Inc. is the project’s contractor. The construction cost is approximately $2,345,000 and is funded with County Road Funds.