Canyon Road East - 400' North of 84th St E to 72nd St E (CRP 5736)

What's Happening


Engineering: We're completing the final engineering for the project. The project is a continuation of a project planned to start construction in April 2020 on Canyon Road East from 99th Street Court East to 84th Street East (CRP 5726).
Image of the project vicinity map.
Image of the project.

About the Project


Planned improvements to Canyon Road East from 400' North of 84th Street East to 72nd Street East (CRP 5736) are intended to enhance safety and relieve traffic congestion, and include the following:
  • Expanding to five lanes with a two-way left-turn lane.
  • Adding concrete curbs, gutters and sidewalks from 400' North of 84th Street East to 72nd Street East.
  • Adding street lighting.
  • Improving the traffic signal at 72nd Street East.
  • Adding an enclosed storm drain system, as well as stormwater treatment and storage facilities.
This project has been identified as a priority by the County Council and is included in the 2019-2024 Transportation Improvement Program (TIP). We also have the Connecting Our Industrial Centers Map outlining the Regional Investment.

Image of the project right-of-way plan cover sheet.
Image of the project typical roadway section.

Project Timeline


June 2016: Completed preliminary engineering and right-of-way plans.

July 2016 to December 2020: Complete final engineering, environmental documentation, and right-of-way acquisitions.

Beyond
: Actual construction is dependent on securing additional funding.