Canyon Road East - 192nd Street East to Frederickson Industrial Park Road East (CRP 5666)

Road with vehicles driving on it

What’s Happening


A Pierce County project to improve Canyon Road East between 192nd Street East and Frederickson Industrial Park Road East will begin April 25. The bulk of the work is expected to be complete by the fall.

Starting April 25, crews will begin installing erosion control measures, construction fencing and construction signage. 

About the work


 Crews will:
  • Widen the road to accommodate a new two-way left turn lane. This section of Canyon Road East currently has two lanes in each direction.
  • Add concrete curbs and gutters
  • Install street lighting
  • Add a combination of concrete and porous sidewalks
  • Resurface the road from 192nd Street East to 187th Street East
  • Add storm drainage facilities
  • Activate a new signal system at the Canyon Road East and 184th Street East intersection. This is expected in late 2018. 
  • Complete final paving and striping. This work will like by done in Spring 2019.

Weekend closures in May


Tacoma Rail will close Canyon Road East from 192nd Street East to 176th Street East for two weekends in May while it upgrades two rail crossings. The first closure will run from 7:30 p.m. on May 4 to 6 a.m. on May 7. The second closure will run from 7:30 p.m. May 11 to 6 a.m. May 14.

Local business access will be maintained during the weekend closures. A detour will take motorists from 192nd Street East to 38th Avenue East to 176th Street East. Please see the detour route map below.

Motorists can contact Tacoma Rail at (253) 396-3161 with questions about the closure.


5666_tacoma_rail_pc

Traffic impacts 


The bulk of construction on Pierce County’s project will begin after May 14. Motorists should expect significant traffic impacts on weekdays throughout the project. Motorists may want to consider taking 192nd Street East to 38th Avenue East to 176th Street East throughout the project to avoid the work area.

Both southbound lanes will be open on weekdays between 4:30 a.m. and 8:30 p.m. Lane restrictions may be in place outside of these hours.

Both northbound lanes will be open 5 a.m. to 8:30 a.m. on weekdays to support the morning commute. Northbound traffic may be reduced to one lane outside of these hours.

Nighttime work may be needed throughout the project. Alternating one-way traffic may be needed on 184th Street East, 187th Street East and 189th Street East during working hours.

Miles Resources is the contractor. The construction cost is approximately $2.5 million. It is funded with County Road Funds.  

Project Timeline 


March 9, 2018: Bid Opening date 

March 20, 2018: Pierce County awarded the contract to Miles Resources LLC

April 11, 2018: Pierce County hosted the Pre-Construction Meeting

April 25, 2018: Anticipated Notice to Proceed 

September 2018: Anticipated Substantial Completion

October 2018: Anticipated Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Miles Resources, LLC
Contractor
Phone: (253) 383-3585
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
400 Valley Ave NE 
Puyallup, WA 98372