62nd Avenue NW / 144th Street NW (CRP 5801)

5801 Intersection Banner

What's Happening


Construction on a project to improve the 62nd Avenue Northwest and 144th Street Northwest intersection will begin April 9. The project is expected to be complete in early 2020.

About the Project


The improvements are intended to improve safety and increase the efficiency of the intersection. Improvements will include the following:
  • Installing a traffic signal system.
  • Providing street lighting on 144th Street Northwest.
  • Adding a westbound left-turn lane on 144th Street Northwest at the intersection.
  • Adding a two-way left-turn lane on 144th Street Northwest from 62nd Avenue Northwest to the school parking lot entrance.
  • Providing a northbound left-turn lane and a right-turn lane on 62nd Avenue Northwest.
  • Constructing retaining walls.
  • Adding stormwater treatment facilities and detention vault.

Construction schedule


The majority of the work will be completed during the summer months to minimize impacts to Peninsula School District students, staff and parents.

From April 9-16, crews will clear bushes and trees, remove guardrails and excavate shoulders.
Utility companies will be onsite relocating utility lines and poles starting April 24.

Construction work will start back up on June 24, with crews installing retaining walls and temporary drainage facilities, and constructing a temporary one-lane bypass road along the shoulder of the east side of 62nd Avenue Northwest. 

While the bypass road is in place, crews will excavate and rebuild 62nd Avenue Northwest. A stormwater detention vault will be installed under the road before the road is rebuilt. The bypass is expected to be removed Aug. 15 and 16.

From late August to early September, crews will widen 144th Street Northwest and continue installing storm drainage facilities and retaining walls.

Utility companies be back onsite Sept. 17 to continue relocation work, with construction resuming Oct. 14. Crews will prepare 144th Street Northwest to be resurfaced and install street lights and the new traffic signal. 

Starting in late October, crews will resurface 144th Street Northwest, apply temporary striping and install guardrails. Final striping is expected in late December or early 2020.

Traffic impacts


During construction, crews will work from 7 a.m. to 3:30 p.m. Monday to Friday. Crews may work until 5:30 p.m. for several weeks this summer when the vault is being installed.

There will be alternating one-way traffic on 144th Street Northwest during work hours throughout the project as needed. 

There will be alternating one-way traffic along 62nd Avenue Northwest 24-hours a day, seven days a week while the bypass road is in place from late June to mid-August.

Active Construction Inc. is the contractor. The construction cost is approximately $2.4 million and is funded with County Road Funds.
Project Timeline
February 01, 2019: Bid Opening date

February 12, 2019: Pierce County awarded the contract to Active Construction


March 18, 2019:
 Pierce County hosted the Pre-Construction Meeting

April 8, 2019:
 Anticipated Notice to Proceed

April 24, 2019: First Utility Window begins

June 24, 2019: Construction resumes

Sept. 17, 2019: Utility Window begins

Oct. 14, 2019: Construction resumes

Late December 2019 or early 2020: Construction complete
Contact Us
Send a message arrow
Chris Estep
Construction Supervisor
Phone: (253) 798-6814
Active Construction
Contractor
Phone: (253) 248-1091
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
5110 River Road East
Tacoma, WA 98443