What's Happening
Engineering: The project is in the early stages of the preliminary engineering phase. Finalizing the roadway layout, and beginning the storm drainage design. Beginning the environmental geotechnical studies.
About the Project
Planned improvements to the intersection of
Sunrise Parkway East / 122nd Avenue East (CRP 5786) are intended to increase efficiency of the intersection and improve safety. Improvements will include the following:
- Adding two southbound left-turn lanes.
- Adding a northbournd left-turn lane.
- Install cement concrete curb, gutter, and sidewalks.
- Install an enclosed storm drainage system, and water quality treatment and storage facilities.
- Install street lighting.
- Install a new traffic signal system.
Project Timeline
March 2018 to December 2018: Topographic survey work of the existing conditions, produce preliminary construction plans, prepare a cost estimate, and finalize right-of-way plans, and complete the Preliminary Engineering Phase.
January 2019 to 2020: Right-of-Way acquisition, environmental permitting, final engineering, and construction of the intersection pending funding availability.