38th Avenue East / 152nd Street East (CRP 5835)

What's happening 


A new traffic signal system was activated at the 38th Avenue East and 152nd Street East intersection on May 5.

The intersection is located to the east of Naches Trail Elementary School.


About the project


Work on the intersection project began in mid-August 2019. Crews installed curbs, gutters, sidewalks and curb ramps at the intersection, along with electrical infrastructure for the new signal. The corners of the intersection were reconstructed to accommodate larger vehicles. Crews repaved the intersection in October. 

The work was put on hold – or suspended – in October while traffic signal poles were being delivered.

Work resumed April 13, with crews installing the signal poles, street lights, signal cabinets and final pavement markings. 

Titan Earthwork LLC is the contractor. The construction cost is approximately $670,000 and is funded with Pierce County traffic impact fees and Federal Highway Safety Improvement Funds.


Project Timeline

April 26, 2019: Bid Opening

May 17, 2019:
Pierce County awarded the contract to Titan Earthwork LLC

June 26, 2019:
Pierce County hosted the Pre-Construction Meeting


August 16, 2019: Notice to Proceed


Late October 2019: Work suspended


April 13, 2020: Work resumes


May 5, 2020: Traffic signal activated


June 25, 2020: Physical Completion

Contact Us


Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913

Address:
2702 S 42nd St, Ste 109
Tacoma, WA 98409

Contractor: 
Titan Earthwork LLC
Phone: (206) 325-3004

Address:
1585 Valentive Ave SE
Pacific, WA 98047