What's Happening
Engineering: We're beginning the preliminary engineering for the project. We'll be completing the field survey of the corridor, vertical alignment design, storm drainage treatment and conveyance design.
About the Project
Planned improvements to
112th Street South from C Street South to A Street South (CRP 5853) are intended to increase capacity and relieve traffic congestion, and include the following:
- Expanding to five lanes with a two-way left-turn lane, with additional turn lanes at the 112 St S / SR 7 intersection
- Adding concrete curbs, gutters and sidewalks.
- Adding street lighting.
- Reconstructing the traffic signal at the 112th St S / C St S intersection.
- Adding an enclosed storm drain system, as well as stormwater treatment facilities.
Project Timeline
July 2017 to September 2017: Complete field surveys.
September 2017 to December 2018: Complete preliminary engineering and right-of-way plans.
December 2018 and Beyond: Right-of-way acquisition, environmental documentation, construction plans, specifications, estimates, and construction. These activities are all dependent on additional funding.