Olson Drive NW / 92nd Street NW - Key Center Sidewalks (CRP 5863)

What’s happening

Work on a project to install sidewalks on a section of Olson Drive Northwest was completed June 30.


The 385-foot section is located to the west of the road’s intersection with Key Peninsula Highway Northwest near Key Center. Crews also widened the road to accommodate new paved shoulders, and added curbs, gutters and storm drainage facilities.


The project’s contractor was Rodarte Construction. The construction cost was approximately $337,000 and was funded with County Road Funds and Washington State County Road Administration Board Rural Arterial Program Funds. 


Image of the project vicinity map.
CRP 5863 - Olson Dr KPN / 92nd St KPN

About the Project

Planned improvements to Olson Drive KPN / 92nd Street KPN from approximately 425 feet west of Key Peninsula Hwy KPN to 75 feet west of Key Peninsula Hwy KPN (CRP 5863) are intended to improve pedestrian accessibility and sidewalk connectivity in the project area and include the following:

  • Widening the roadway to include asphalt paved shoulders
  • Adding concrete curbs, gutters, and sidewalks.
  • Adding an enclosed storm drain system, as well as stormwater treatment facilities.
Image of the project roadway section.
Image of the R/W Plan Cover Sheet.

Project Timeline

February 28, 2020: Bid Opening date


March 9, 2020: Pierce County awarded the contract to Rodarte Construction.


April 15, 2020: Pierce County hosted the Pre-Construction Meeting


April 28, 2020: Construction begins


June 30, 2020: Physical Completion

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409

Rodarte Construction
Contractor
Phone: (253) 939-0532

Address:

17 East Valley Hwy E

Auburn, WA 98029