ADA Improvement Program - 2019

What's happening?


A project to improve accessibility in the vicinity of 177th Street East and 180th Street East west of 38th Avenue East began July 15. The work is expected to be complete in early August.

Crews are in the process of installing curbs and gutters.

About the project


Crews will remove and reconstruct existing curb ramps and add new curb ramps that are in compliance with current Americans with Disabilities Act standards. Click on the "Project Location" icon above to view a map showing where the work will occur.

Impacts


Work hours will be 7 a.m. to 3:30 p.m. Monday to Friday. Lane restrictions will be needed in work areas. Pedestrian access will also be restricted.

The contractor is Four Seasons Concrete Construction LLC. The construction cost is approximately $217,000. This project is funded with County Road Funds.

Project Timeline

April 5, 2019: Bid Opening date

April 15, 2019: Pierce County awarded the contract to Four Seasons Concrete Construction

June 18, 2019: Pierce County hosted the Pre-Construction Meeting

July 15, 2019: Anticipated Notice to Proceed 

August 2019: Anticipated Substantial and Physical Completion

Contact Us


Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913

Four Seasons Concrete Construction
Contractor
Phone: (253) 301-3858

Address:
2702 South 42nd Street, Suite 109
Tacoma, WA 98409

Address:
5309 84th St E
Tacoma, WA 98446