What's Happening 


Pierce County hosted the Pre-Construction Meeting on December 5, 2018, and anticipates issuing the Notice to Proceed on December 12, 2018. When the work begins, the Contractor, Petersen Brothers Inc., will be on-site installing the beam guardrail.

About the Project

This contract provides for the improvement of various roadways by installing beam guardrail, and guardrail reflector tabs.

  • Group 1: Fox Drive FI
  • Group 2: Bridge #29184-A (70th Ave E at North Fork Muck Creek)

Project Timeline


September 21, 2018:
 Bid Opening
 date

November 8, 2018: Pierce County awarded the contract to 
Petersen Brothers Inc.

December 5, 2018:
 Pierce County hosted the Pre-Construction Meeting

December 12, 2018:
 Anticipated Notice to Proceed

January 2019: Anticipated Substantial Completion

January 2019: Anticipated Physical Completion


Contact Us
Send a message arrow
Chris Estep
Construction Supervisor
Phone: (253) 798-6814
Petersen Brothers, Inc
Contractor
Phone: (253) 863-8136
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
2008 East Valley Hwy E
Sumner, WA 98390