Traffic signal system coming to 38th Avenue East and 152nd Street East intersection May 5

A new traffic signal system will be activated at the 38th Avenue East and 152nd Street East intersection on May 5.

The activation is weather dependent. The intersection is located to the east of Naches Trail Elementary School.

Work on the intersection project began in mid-August 2019. Crews installed curbs, gutters, sidewalks and curb ramps at the intersection, along with electrical infrastructure for the new signal. The corners of the intersection were reconstructed to accommodate larger vehicles. Crews repaved the intersection in October.

The work was put on hold – or suspended – in October while traffic signal poles were being delivered. Work resumed April 13, with crews installing the signal poles, street lights, signal cabinets and final pavement markings.

Titan Earthwork LLC is the contractor. The construction cost is approximately $670,000 and is funded with Pierce County traffic impact fees and Federal Highway Safety Improvement Funds.

A project webpage is available at www.piercecountywa.gov/crp5835.

MEDIA CONTACT:
Anne Radford, Pierce County public information specialist
(253) 798-2464
anne.radford@piercecountywa.gov

Facebook Twitter Email

Other News in Planning & Public Works

Groundwater Monitoring Season Reminder

Posted on: October 9, 2020

Natural Disaster Assistance

Posted on: September 15, 2020

Critical Area Sign-Off Improvements

Posted on: November 19, 2019

October News - Community Plan Updates

Posted on: October 18, 2019

Code enforcement portal improvements

Posted on: September 26, 2019

Our permit process just got easier

Posted on: September 24, 2019

Recording Fees Increase in July 2019

Posted on: July 10, 2019

Shoreline Master Program Update

Posted on: June 20, 2019

Road standards revisions coming soon

Posted on: March 13, 2019

Apply for Family Wage Job Credits

Posted on: March 8, 2019

February 28 Traffic Impact Fee Workshop

Posted on: February 19, 2019

West Lobby at the Annex Closes March 1

Posted on: February 14, 2019

Traffic Impact Fees To Change Feb. 1

Posted on: January 28, 2019

Annex Remodel Underway

Posted on: January 18, 2019

January 16 Shoreline Workshop

Posted on: January 9, 2019

Family-Wage Job Credit Program

Posted on: January 2, 2019

Tips to treecycle your Christmas tree

Posted on: December 20, 2013

New levee will protect people, help salmon

Posted on: December 19, 2013

Treecycle your Christmas tree

Posted on: December 24, 2012
Santa photo

See Santa land at Thun Field, Dec. 9

Posted on: December 4, 2012

Prepare now for flood season

Posted on: October 19, 2012

Ferry crew rescues kayaker

Posted on: September 7, 2012

Wednesday ferry schedule adjusted

Posted on: June 15, 2012

Celebrate Puget Sound in May

Posted on: April 25, 2012

Last chance for free storm debris disposal

Posted on: February 24, 2012

Free storm debris disposal ends Feb. 26

Posted on: February 17, 2012